STAGE TWO - INSTALLING DRYWALL and ELECTRICAL, PRIMING and PAINTING

Drywall is installed on the ceiling and cement board is installed in the bath area.

Electrical is installed.

Boxes for the bathroom outlet and exhaust/light switches.

The housing unit for the ceiling exhaust/light.

Another outlet was installed for the jacuzzi water heater.

A new outlet is installed in the bedroom.

Another outlet is installed in the bedroom.

Boxes for the closet and bathroom light switches.

Inspection for electrical and plumbing.

Drywall is installed on the walls.

The shower area.

Housing unit for the ceiling exhaust/light.

The toilet area.

The sink area.

Where the mirror, light switches and electrical outlets will be installed.

For the light above the sink.

First coat of primer is applied.

Crown molding is installed.

The first coat of paint is applied.